Projects

Installation & Commissioning Works

  • Clients

    Siemens
  • Locations

    Cowley 400kV Substation
    Minety 400kV Substation
  • End User

    National Grid

Services Provided

  • Installation

    Yes
  • Site Management

    Yes
  • Commissioning

    Yes
  • Design

    No
  • Health & Safety

    Yes

Project Description

COWLEY + MINETY 400kV
• Installation of NICAP Protection Panels / multicore / GPS Antenna
• Removal of redundant protection, control panels and telecoms equipment at each substation
• Installing and testing of fibre optics on both sites
• Installing new MCBs within existing VT boxes
• Installation of High Frequency Earthing positions on existing CVTs at each substation
• Commissioning of the NICAP Protection
• Providing site management to co-ordinate activities on site with Siemens and National Grid where applicable

Project Highlights


The sites were established on the 14th march 2011 and the project will run until the end of May.

All pre outage work was complete within the allocated time.
The outage work has progressed in line with the programme, despite the RHMZ being enforced due to the ‘FMJL CT’ issue. RTS to be achieved in line with the programme

Client Feedback