





INDIAN QUEENS 400kV SUBSTATION – Main Scope of Work is Circuit Breaker Replacement.
• Substation Engineering Services will replace the following equipment;
o 3 off FMLG CTs and 3 off CVTs on the Landulph 2 circuit.
o 2 off CTVs on the Taunton 1 circuit.
• SES will also Dismantle, Remove and Dispose of the existing 400kV AT4ML ABCB, 2 sets of 400kV CTs and steel support structures; including the marshalling Kiosk, as well as the associated air pipework, busbars and connections.
• Installation of a new Mitsubishi 400kV Circuit Breaker along with the associated Marshalling Kiosk.
• Installation of Mechanical and Electrical Interlocks
• Modification of existing Protection
• Installation of 6 x 400kV CTs and associated Busbars Clamps and Fixings
• Multicore Cable Laying, Glanding and Termination
• Installation of above ground Earthing for the new CB and CTs, and High Frequency Earthing of the CVTs
“The SES site manager and his team have worked well together with the National Grid SAP in delivering this project on time” – Karl Gatcum, SWA