Projects

 

  • Clients

    ABB
  • Locations

    Thornton / Creyke Beck
  • End User

    National Grid

Services Provided

  • Installation

    Yes
  • Site Management

    Yes
  • Commissioning

    Yes
  • Fibre Optics

    Yes
  • Health & Safety

    Yes

Project Description

Seabank Protection Room

Removal of existing protection panels at both Thornton and Creyke Beck substations. Installation of new panels and associated multicore cables. Line Trap removal and associated high frequency earthing, fibre optic installation at Creyke Beck. Full scheme commissioning and TP144 site management.

Project Highlights

Client Feedback